In this five-part series, I expose and disprove NIST's false claims in five critically important areas:
Part 1: Burned-Out Fire
Part 2: Magical Thermal Expansion
Part 3: Missing Shear Studs
Part 4: Fictitious Debris Damage
Part 5: Non-Existent Diesel Fuel Fire
Note: Quotes from NIST's WTC 7 reports are shown in Bold Light Blue.
NIST used numerous unscientific methods and fraudulent inputs to get the key girder to fail in its computer simulation.
For example, NIST arbitrarily added 10% to the temperature results of its fire dynamics simulation (FDS).
“Case A used the temperature data as obtained from the FDS simulation. Case B increased the Case A gas temperatures by 10 percent.” — NCSTAR 1A, page 32 [PDF page 74]
“[O]nly the fire-induced damage produced by Case B temperatures was carried forward as the initial condition for the building collapse analysis.” — NCSTAR 1A, page 36 [PDF page 78]
To get the shear studs on the floor beams to fail, NIST had to assume high steel temperatures. It applied the heat in 1½ seconds over the entire northeast part of Floor 13. This faulty method of calculating temperatures, though, does not allow for the reality of heat dispersal or for the inevitable beam sagging.
Interestingly, NIST's model heated the floor beams but not the concrete slab. Since concrete expands at 85% the rate of steel, leaving this expansion out of the calculations of the shear studs failure is fraudulent.
“The girder and beam temperatures were assumed to be 500° C and 600° C, respectively, and the slab was assumed to remain unheated.” — NCSTAR 1-9, Vol. 1, page 349 [PDF page 393]
“Ramping of the temperatures for the beams and the girder then commenced at 1.1 s, leveling off at temperatures of 600° C for the beams and 500° C for the girder at 2.6 s. These temperature histories were prescribed uniformly for all nodes of the beams and the girder, respectively.” — NCSTAR 1-9, Vol. 1, page 352 [PDF page 396]
“The first failures observed were of the shear studs, which were produced by axial expansion of the floor beams, and which began to occur at fairly low beam temperature of 103° C. . . . When the beam temperatures had reached 300° C, all but three shear studs in the model had failed due to axial expansion of the beams, leaving the top flanges of the beams essentially unrestrained laterally.” — NCSTAR 1-9, Vol. 1, page 352 [PDF page 396]
“This analysis demonstrated possible failure mechanisms that were used to develop the leading collapse hypothesis further. The failure modes in this model were incorporated into the 16-story ANSYS and 47-story LS-DYNA analyses.” — NCSTAR 1-9, Vol. 1, page 353 [PDF page 397]
NIST assumed that it took 90 minutes for the fires—which it said were started by burning debris from WTC 1 some 350 feet away—to develop into a 2MW (megawatt) fire.
“The choice of a 2 MW fire at 12:00 noon was a somewhat arbitrary initialization of the simulations, but there is little visual evidence of how the fires behaved in the time period between 10:28:22 a.m. and 2:00 p.m. . . . starting the calculations at noon was convenient in that the simulation time was the same as the actual clock time.” — NCSTAR 1-9, Vol. 2, page 377 [PDF page 38/443 in combined Vol. 1 and Vol. 2]
In NIST's scenario, the damage and the collapse would have occurred at 4:00 p.m.
“The building response is examined at 3.5 h and 4.0 h of heating. At 3.5 h, the floor systems had fire-induced damage and failures of some connections, beams, and girders. After 4.0 h of heating, there was substantially more damage and failures in the WTC 7 structural floor system, particularly in the northeast region surrounding Column 79. The structural condition at these two times illustrates how the structure developed sufficient fire-induced damage to reach the collapse initiation event.” — NCSTAR 1-9, Vol. 2, page 493 [PDF page 155/559]
Building Response at 4.0 h
“On Floor 13 (Figure 11–35), all four of the north-south girders attached to Columns 79, 80, and 81 had failed, due to either buckling or girder walk off of the bearing seat at Columns 79 and 81.” — NCSTAR 1-9, Vol. 2, page 504 [PDF page 166/570]
“Fire-induced thermal expansion of the floor system surrounding Column 79 led to the collapse of Floor 13, which triggered a cascade of floor failures. . . . This left Column 79 with insufficient lateral support, and as a consequence, the column buckled eastward, becoming the initial local failure for collapse initiation.” — NCSTAR 1A, page 22 [PDF page 64]
NIST assumed that all the expansion would occur on one end of the floor beams, which is quite impossible. Furthermore, NIST failed to account for beam sag that would have prevented the floor beams from expanding lengthwise more than 5.392 inches at 600° C even if all the expansion were on one end.
Table 10-1 shows that the floor beams under floor 13 did not exceed 600° C in the northeast section.
Without loss of length due to sagging, at 600° C the floor beams would have expanded 5.517 inches, which is why NIST said that the seat was only 11 inches wide in the final report. Had NIST taken sag into consideration, it would have shortened the beams by 1/8 inch, to 5.392 inches at 600° C — not enough to cause failure, even if the seat were only 11 inches wide.
“A girder was considered to have lost vertical support when its web was no longer supported by the bearing seat. The bearing seat at Column 79 was 11 in. wide. Thus, when the girder end at Column 79 had been pushed laterally at least 5.5 in., it was no longer supported by the bearing seat.” — NCSTAR 1-9, Vol. 2, page 527 [PDF page 189/593]
An errata published by NIST in 2012 corrected the “mistake” (about the width of the column seat) that had been made in the final report.
“The bearing seat at Column 79 was 11 12 in. wide. Thus, when the girder end at Column 79 had been pushed laterally at least 5.5 6.25 in., it was no longer supported by the bearing seat.” See June 2012 Text Changes to the NIST Reports.
By acknowledging that the seat was in fact 12 inches wide, NIST is admitting that thermal expansion could not have caused the girder to fail; therefore, its hypothesis fails.
Note that the maximum expansion is 5.728 inches at 654° C, because loss due to sagging exceeds elongation due to thermal expansion after that.
As shown in the graph, structural steel sags as temperature rises, decreasing its length and negating the thermal expansion that NIST blames for the collapse of WTC 7.
But the impossibilities don't stop there. Another thing that makes walk-off impossible is that even if the floor beams could have expanded 6.25 inches on one end and even if no sagging had occurred, the side plate on column 79 would have prevented the girder from falling off its seat. The girder would have expanded in length until it was pressing up against the column between the side plates.
NIST ignored its own finding:
“Temperatures were uniform (within 1° C) across the bottom flange and web, but the top flange temperature was less by up to several hundred degrees because the slab acted as a heat sink.” — NCSTAR 1-9, Vol. 2, page 391 [PDF page 53/457]
Thermal expansion would cause the bottom flange to expand more than the top flange, forcing the beam to bow downward. The NIST hypothesis does not allow for downward bowing.
But NIST said that the critical damage occurred at temperatures below 400° C.
“The initiating local failure that began the probable WTC 7 collapse sequence was the buckling of Column 79. This buckling arose from a process that occurred at temperatures at or below approximately 400° C (750° F).” — NCSTAR 1A, page 21 [PDF page 63]
“Fire-induced thermal expansion of the floor system surrounding Column 79 led to the collapse of Floor 13, which triggered a cascade of floor failures. In this case, the floor beams on the east side of the building expanded enough that they pushed the girder spanning between Columns 79 and 44 to the west on the 13th floor. This movement was enough for the girder to walk off of its support at Column 79.” — NCSTAR 1A, page 22 [PDF page 64]
In the temperature and sag spread sheet above, 400° C would expand the 53-foot floor beams only 3.3 inches.
Pursuant to a FOIA request by AE911Truth structural engineer Ron Brookman, NIST finally released the structural and shop drawings in January 2012.
They can be downloaded here: WTC 7 Blueprints Exposed Via FOIA Request: Building Plans Allow for Deeper Analysis of Skyscraper’s Destruction.
Ron Brookman reviewed the hundreds of drawings through 2011 and then, in February 2012, shared several sheets and the data file with David Cole and his research team. In Frankel drawing #1091, which shows the girder seated connection at Column 79, Cole noticed that the girder seat was 12 inches wide (as noted above), not the 11 inches claimed in the November 2008 final report. In Frankel #9114 he also noticed the web/flange stiffeners on girder A2001, at the floor 13 Column 79 connection.
NIST omitted these web/flange stiffeners that would have prevented the bottom flange from folding as required for their collapse to begin. The girder would have to be pushed almost all the way off the seat, not just half way, before the bottom flange would buckle.
NIST was informed of the dimensional discrepancy and their failure to include the stiffeners in their graphic of the girder connection. In June 2012, NIST corrected their report in an errata (see here: https://ws680.nist.gov/
In late October 2013, NIST finally admitted that they did not include the stiffeners in their finite element analysis. Their rather puzzling excuse was that since the web did not buckle it was not necessary to include the web stiffeners in the graphic or finite element analysis (even though they would have prevented the bottom flange from folding and thus preventing the girder from failing).
“Walk-off failure of beams and girders was defined to occur when. . . . the beam or girder was pushed laterally until its web was no longer supported by the bearing seat. . . . [T]he beam was assumed to have lost support, as the flexural stiffness of the bottom flange was assumed to be insufficient for transferring the gravity loads.” — NCSTAR 1-9, Vol. 2, page 488 [PDF page 150/554]
The web/flange stiffeners are on the Frankel drawings, but not on the NIST drawings in the final report.
Thanks to the persistence of researcher David Cole, NIST admitted that they omitted the web/flange stiffeners. See: http://911blogger.com/news/2013-11-06/nist-replies-stiffeners-inquiry
NIST’s drawing of column 79 omits the web/flange stiffeners that would have prevented the girder's failure.
Frankel’s original column drawings (above and below) show the 3/4” web/flange stiffeners in place.
References:
NCSTAR 1A Final Report on the Collapse of World Trade Center Building 7
NCSTAR 1-9, Vol.1 and Vol. 2 Structural Fire Response and Probable Collapse Sequence of World Trade Center Building 7